Kentucky has roughly 1,226 MW of utility-scale solar operating across 20 farms, and thousands more megawatts moving through the interconnection queue behind it. Most of the built capacity sits on farm ground in the western half of the state, where water has been the limiting factor on row-crop yield for decades.
Abraham Drainage & Excavating is a veteran-led drainage contractor serving EPC firms, solar developers, and engineering teams building utility-scale solar in Kentucky. Kentucky work runs through the same renewable energy drainage practice we operate across the Midwest. We find the tile before the pile driver does, hold the ground stable through construction, and hand over records that satisfy the Division of Water, the Siting Board, and the landowner whose field is next door.
Straight answer on our footprint: our built work is in Ohio, Indiana, Illinois, Michigan, New York, and Wisconsin. Kentucky is a market we are entering, and we would rather say that than let a page imply otherwise. What transfers is the ground. The Ohio River bottoms that run through Henderson and Union Counties are the same alluvial system our Indiana crews work across the river, and the tile in them was installed by the same generation of farmers for the same reason.
On former farm ground in Kentucky, utility-scale solar sites frequently run into:
What that costs when it is missed:

That work is backed by 15.8 million feet of pipe installed across the Midwest, 291 completed projects, and more than 26,100 acres evaluated for drainage risk. Kentucky projects draw on that record from day one.
Why Choose Us
Why Kentucky Project Teams Bring Us In
Western Coal Field and Ohio Valley (Henderson, Union, Webster, Daviess Counties):
The center of gravity for Kentucky solar. Sebree Solar covers roughly 2,100 acres in Henderson County across two phases, with Phase I online at 250 MW since September 2025 and Phase II adding 150 MW. Unbridled Solar operates 160 MW across Henderson and Webster Counties. This is wide, flat, poorly drained ground with the state’s most active row-crop tile installation. Legacy tile density and outlet protection drive site planning here, and undocumented lines are the single largest change-order risk on these sites.
Jackson Purchase (Ballard, Graves, McCracken, Hickman Counties):
Kentucky’s far western tip, and an active part of the development pipeline. Gage Solar is planned at roughly 240 MW in Ballard County. Mayfield Solar and Storage is planned at 200 MW across roughly 1,869 acres in Graves County. The ground is loess over coastal plain sediment: flat, silty, and prone to perching water above a fragipan. Standing water shows up here without a shallow water table to explain it. Surface grading and underdrain work carry more weight than deep tile.
Pennyroyal and Karst Country (Logan, Todd, Barren, Metcalfe, Lyon, Meade Counties):
SR Russellville carries 173 MW in Logan County. Glover Creek Solar operates 55 MW in Metcalfe County and Ashwood Solar I 86 MW in Lyon County. Green River Solar puts 200 MW on the ground across Breckinridge and Meade Counties, where the karst plain runs north to the Ohio River. This is Mississippian limestone with sinkholes, caves, and subsurface channels under it. Standing water is rarely the problem. Sediment leaving the site through an open karst feature and into groundwater is. Erosion control here is a groundwater protection scope, not a checklist item.
Bluegrass (Harrison, Mason, Garrard, Bourbon Counties):
Bluebird Solar operates 100 MW in Harrison County and SR Turkey Creek 50 MW in Garrard County. Goldfinch Solar is in development at up to 250 MW in Mason County. Limestone and shale under rolling ground, with sinking streams and springs. Grade control and outlet placement matter more here than tile volume. Garrard County also reaches into the Knobs, where shallow bedrock changes what trenching costs before the first machine moves.
Eastern Coal Field Reclaimed Mine Ground (Martin, Perry, Knott, Breathitt Counties):
Martin County Solar put 111 MW on 850 acres of the former Martiki mine and reached commercial operation around the turn of 2024 into 2025. The Starfire project is planned at 410 MW across Perry, Knott, and Breathitt Counties in four phases, with the first phase approved for construction in 2025. Compacted spoil, engineered benches, and rebuilt drainage patterns behave nothing like native soil. Infiltration assumptions carried over from a farm site will not hold. We price that ground on its own terms.
Kentucky does not sit alone in our footprint. Cross the river from Henderson County and our Indiana solar drainage work is standing on the same alluvium and the same generation of tile. Farther west, our Illinois solar drainage projects sit on the loess and bottomland that continue into the Jackson Purchase.

Siting, at the State Board on Electric Generation and Transmission Siting.
Under KRS 278.700 through 278.716, a merchant electric generating facility with an aggregate capacity of 10 MW or more must obtain a construction certificate from the Siting Board before construction begins. Utility-owned generation follows a separate PSC certificate path instead, and projects under 10 MW answer to local zoning alone.
House Bill 4, effective June 28, 2023, changed the terms. Certificate validity moved from two years to three. A decommissioning plan and bond became mandatory application elements rather than conditional add-ons. The bond is set by an independent licensed engineer on the net present value of decommissioning cost less salvage value, or the amount a local ordinance requires, whichever is greater, and the Cabinet reviews it at least every five years. Local planning and zoning commissions hold primacy on setbacks and on decommissioning, and the Siting Board cannot waive what a local commission sets. On a Kentucky site the county is not a formality.
Stormwater, at the Kentucky Division of Water.
The KPDES KYR10 general permit covers land-disturbing construction of one acre or more, including contiguous activity inside a larger common plan of development that cumulatively disturbs one acre or more. The Notice of Intent goes in at least seven days before construction starts, and authorization is effective only when the Division of Water issues written notification of coverage. Filing is not coverage. The SWPPP has to be developed specific to the site. Inspections run at least once every seven calendar days, or at least once every fourteen calendar days paired with an inspection within 24 hours of any storm event of 0.5 inch or greater. Records are retained at least three years from termination of coverage or expiration of the permit.
Farm ground, at the county conservation district.
The Kentucky Agriculture Water Quality Act, KRS 224.71-100 through 224.71-140, requires landowners with 10 or more contiguous acres in agriculture or silviculture to develop and carry out an Agriculture Water Quality Plan built on statewide best management practices. The Division of Conservation administers it and local conservation districts provide the technical assistance. Where solar lands on leased farm ground, the landowner’s plan does not disappear. Separately, drainage districts organized under KRS Chapter 267 and county ditches under KRS Chapter 269 carry their own board approvals and outlet rights. Under KRS 267.450, a landowner assessed for the cost of a drainage improvement may use that improvement as an outlet for lateral drains. Where a project touches one, that gets identified before design is locked.
Groundwater, where karst is present.
401 KAR 5:037 requires groundwater protection plans for a defined list of activities, including bulk fuel and chemical storage and handling and the installation or abandonment of wells and bore holes. Several of those land on a solar construction site even though land-disturbing construction itself is not on the list. In karst terrain that matters more than the regulation’s narrow scope suggests, because a sinkhole is a direct route from the surface to an aquifer with no soil in between.
01
Site Walk and Region Check
We walk the site with your project management or civil team to locate known drainage features and confirm which Kentucky region we are working in. That means checking for organized drainage districts and county ditches, mapping sinkholes and closed depressions where karst is in play, and interviewing landowners about tile nobody wrote down. Findings are GPS-documented and handed back before they become field surprises.
02
Scope, Price, and Named Risk
You receive a detailed proposal covering scope, pricing, materials, and schedule. We name where change-order risk actually sits on your site: undocumented tile density in the Ohio Valley counties, karst voids and shallow bedrock in the Pennyroyal, perched water over fragipan in the Purchase, or compacted spoil on reclaimed mine ground. If a drainage district or conservation district approval is needed, we identify it here and say who files it.
03
Field Execution and Daily Records
Our crews work alongside your construction team and respond to tile encounters the day they happen. We document work with GPS coordinates and photography as it goes, and we support the KYR10 inspection record, including the entries triggered within 24 hours of a half-inch rainfall.
04
Closeout Package Handover
Before turnover we verify drainage performance and assemble the package: GPS tile maps showing line locations and repair points, erosion control and SWPPP documentation in the form KYR10 requires, records supporting Siting Board and county conditions, and the landowner record for every line we touched, with locations and repair verification.
05
Support Through Later Phases
Phases get added and conditions change. We stay reachable through construction and mobilize for scope additions, added controls, or drainage that a later phase turns into a problem.